Skip to content

Factory

Pabrik Ciki - Bandung

  • Completed
  • Rancaekek, Kabupaten Bandung
  • Cleanroom Panel
  • 5000m2
Pabrik Ciki - Bandung

Overall view — Pabrik Ciki - Bandung

Floor Area
50.002
Panel Thickness
100 mm
Duration
12 minggu
Year
2026

01 / Project Summary

About This Project

Pabrik Ciki in Rancaekek, Kabupaten Bandung was carried out using a panel cleanroom system. The installation focused on clean, precise, standard-compliant results, with field coordination that kept operations running smoothly throughout.

The cleanroom panel system was installed on the walls and ceiling with a smooth, non-porous surface that is easy to sanitize. Every joint is flush with a hidden-screw system and radius coving at the wall-to-floor junctions, leaving no gaps for dirt to collect.

02 / Scope of Work

What We Delivered

  • Cleanroom wall & partition panel installation
  • Production-area ceiling panel installation
  • Flush hidden-screw jointing system
  • Radius coving at wall-to-floor junctions
  • Inspection door & window installation
  • Hygienic finishing & final cleanup

03 / Technical Specifications

Installation Technical Details

Location
Rancaekek, Kabupaten Bandung
Region
Kabupaten Bandung
Category
Factory
Panel Type
Cleanroom Panel
Panel Thickness
100 mm
Floor Area
5000m2
Duration
12 minggu
Application
Dinding & ceiling cleanroom area produksi
Year
2026
Status
Completed
Documentation
1 photos

04 / Challenge & Solution

Our Approach

Challenge

A factory often has to keep running partially during installation, so the work must be split into zones on a tight schedule to avoid disrupting production.

Our Solution

Our team scheduled phased installation outside peak production hours and used pre-fabricated panels to minimize on-site installation time.

05 / Photo Documentation

Project Gallery

1 photos · click to enlarge

Keep in Touch

Ready to Start Your Project?

Contact us for a free consultation and competitive quote